The Challenge…

PHASE I – INTERIM RECOMMENDATIONS

The development of the Historic Structure Report resulted in the identification of critical needs requiring immediate or short-term resolution.  Addressing these issues as the highest priority is necessary to maintain a safe environment for the building and its occupants as well as to arrest deterioration that if left unchecked will result in the continued loss of historic fabric.  

PHASE I Cost Summary

             Address Fire Marshall Recommendations                     $ 2,500

             Install Temporary Rainwater Distribution System          $ 5,000 

             Install Structural Shoring and Interim Reinforcement      $ 3,000

             Conduct Critical Maintenance of Mechanical System    $ 3,100

             Conduct Critical Electrical System Repairs                   $ 13,000

             Conduct Critical Plumbing System Repairs                   $ 1,000

             Conduct Critical Landscape Maintenance and Repair   $ 11,000

             Add Staff Position (Director)                                       $ 45,000

The HSR’s interim recommendations also include opportunities for further study and investigation that will provide a deeper understanding of the property and its components, thereby informing the restoration process.

             Landmark Museum Designation                                   $ 2,500

             Develop Furnishings Plan                                             $ 15,000

             Conduct Comprehensive Paint Analysis                        $ 25,000

             Develop Archaeology Management Plan                      $ 5,000

TOTAL FOR PHASE I                                                             $ 131,100

 

PHASE II – RESTORATION AND INTERPRETATION

Phase II of the project will realize the vision held by the Orange Hall Foundation to preserve and restore the building and its landscape, and present to the public an accurate and inclusive interpretation of its history. 

PHASE II Cost Summary

             Comprehensive Archaeological Investigation                      $ 250,000

             Building Restoration                                                          $ 2,281,742

             New Building Systems                                                      $ 1,225,462

             Landscape Restoration and Site Development                   $ 651,001

             Furnishings and Interpretation                                           $ 500,000

             Design, Testing and Related Costs                                    $ 453,622

TOTAL FOR PHASE II                                                                $5,361,827